Lyon Engineering opens new Washington office:
On March 1, 2009 Lyon Engineering will open its
new Oak Harbor office on Whidbey Island. This office will provide engineering
& surveying services to our private, commercial, and municipal clients.
Look for more information on our website in the next few months.
-
City of Prescott Water System Upgrades
The City of Prescott recently awarded Lyon Engineering
a 1.25 million dollar engineering contract for infrastructure design. The projects consist of over two miles of new water and
sewer trunk mains, a 3.25 million gallon tank, booster station, and region
sewage lift station.
-
Napa Valley Wine Train
Suulutaaq, Inc., an Alaska Native Owned construction
company, has hired Lyon Engineering as project surveyors for the Napa Valley
Wine Train (NVWT) project located in the City of Napa, CA. The project consists
of approximately a mile of new railway track, roadway and utility improvements,
and two new bridges. Proposed completion of the $63 million dollar project is
expected in the summer of 2012.
-
Granite Dells Estates Properties
Granite Dells Estates recently chose Lyon
Engineering as their project engineer for the Granite Dells Estates (GDE)
master planned community in Prescott, AZ. The GDE development will contain 550
residential lots, 67 acres of general business development, and 75 acres of
industrial development. Phase 1 design is scheduled for completion in the
spring on 2009.
-
Hobby Lobby
Kitchell Development recently hired Lyon Engineering
as the design engineer for the new Hobby Lobby in Prescott Valley, Arizona.
Construction is estimated to begin in the spring of 2009.
-
Chino Valley Sewer Extension
The Highlands Ranch to Chino Town Center sewer main extension project, designed by Lyon Engineering,
is estimated to start construction in February of 2009. The 400 thousand dollar
project consists of 4600 lineal feet of 18” sewer main to service the Town of
Chino Valley. Lyon Engineering will be providing the construction management
and inspection for this project
-
City of Prescott Zone 12 Water Extensions
Lyon Engineering is the design engineer and is currently providing construction management and
inspection services for the project. Construction started on November 17, 2008 and is
approximately 60% complete. Asphalt Paving and Supply Inc. was awarded the contract based on their bid of
approximately 1.6 million. The project consists of approximately 6,286 lineal feet of 18”-ductile iron water main,
3,434 lineal feet of 12”-ductile iron water main, two pressure reducing valve
and vaults, and three jack and boring locations.
|