Airport Water Redamation Facility Expansion Phase 1
Lyon Engineering working with Waterworks Engineering was chosen to design a new 3.75 million gallon a day
water reclamation facility for the City of Prescott. This new facility will replace the current facility
that has a maximum capacity of 1 million gallons per day. The project is located at the existing Airport
Water Reclamation facility near the Prescott Airpark. This project will utilize the Construction manager
at Risk (CMAR) delivery method. Lyon Engineering will support Waterworks Engineering with survey, grading
and drainage, sewer infrastructure, and post design services. Lyon Engineering will provide the City with
a stand alone “Road Map” document that includes the various components and activities required for the
potential conversion of the system from a Decentralized to a Centralized system. The Road Map will include
timelines, costs and operational implications expected for each component. The main areas expected to be
impacted by the potential conversion to the Centralized option.
-
Granite Creek Floodplain Delineation
Lyon Engineering has been contracted to perform a detailed floodplain/floodway analysis of Granite Creek for the
City of Prescott, Arizona and FEMA. We have completed a thorough field investigation of existing conditions and
Manning’s value determination from the Watson Lake Dam to the confluence of Bottleneck Wash, north of the
Prescott Municipal Airport. Lyon is analyzing and mapping the 10, 50, 100, and 500-year floodplains as well as the
100-year floodway. Utilizing BOSS RiverCAD and HEC-RAS, we are updating the current FEMA Approximate Zone A to a
detailed study of Zone AE with Floodway.
-
SR20/Erie Street Storm Drain Reconfiguration
Lyon Engineering is designing a reconfiguration of storm drain systems for the City of Oak Harbor, Washington.
Recent flooding problems have caused the city to contract Lyon to redirect drainage from flowing east along SR20 to south
along Bayshore Drive. This redirecting of the drainage will not only reduce the flooding along SR20, but will also
allow the runoff to outlet to Oak Harbor as it historically did, through the Freund Marsh area. Lyon performed
detailed survey of the existing infrastructure and will complete the construction staking for the reconfiguration.
-
Chino Valley Area Drainage Master Study
Lyon Engineering has recently completed the Area Drainage Master Study for the Town of Chino Valley, Arizona. This study included
analyzing the hydraulics and delineating the floodplains in washes and tributaries throughout the town. Lyon utilized the FLO-2D
modeling software and created a report and master exhibit for existing conditions. A matrix of potential drainage improvements
were created, ranking several considerations for feasibility.
-
Lyon Engineering opens new Washington office:
Lyon Engineering opened a new office in Oak Harbor on Whidbey Island. This office will provide engineering
& surveying services to our private, commercial, and municipal clients.
-
City of Prescott Water System Upgrades
The City of Prescott recently awarded Lyon Engineering
a 1.25 million dollar engineering contract for infrastructure design. The projects consist of over two miles of new water and
sewer trunk mains, a 3.25 million gallon tank, booster station, and region
sewage lift station.
-
Napa Valley Wine Train
Suulutaaq, Inc., an Alaska Native Owned construction
company, has hired Lyon Engineering as project surveyors for the Napa Valley
Wine Train (NVWT) project located in the City of Napa, CA. The project consists
of approximately a mile of new railway track, roadway and utility improvements,
and two new bridges. Proposed completion of the $63 million dollar project is
expected in the summer of 2012.
-
Granite Dells Estates Properties
Granite Dells Estates recently chose Lyon
Engineering as their project engineer for the Granite Dells Estates (GDE)
master planned community in Prescott, AZ. The GDE development will contain 550
residential lots, 67 acres of general business development, and 75 acres of
industrial development. Phase 1 design is scheduled for completion in the
spring on 2009.
-
Hobby Lobby
Kitchell Development recently hired Lyon Engineering
as the design engineer for the new Hobby Lobby in Prescott Valley, Arizona.
Construction is estimated to begin in the spring of 2009.
-
Chino Valley Sewer Extension
The Highlands Ranch to Chino Town Center sewer main extension project, designed by Lyon Engineering,
is estimated to start construction in February of 2009. The 400 thousand dollar
project consists of 4600 lineal feet of 18” sewer main to service the Town of
Chino Valley. Lyon Engineering will be providing the construction management
and inspection for this project
-
City of Prescott Zone 12 Water Extensions
Lyon Engineering is the design engineer and is currently providing construction management and
inspection services for the project. Construction started on November 17, 2008 and is
approximately 60% complete. Asphalt Paving and Supply Inc. was awarded the contract based on their bid of
approximately 1.6 million. The project consists of approximately 6,286 lineal feet of 18”-ductile iron water main,
3,434 lineal feet of 12”-ductile iron water main, two pressure reducing valve
and vaults, and three jack and boring locations.
|